Ultrafiltration Installation Checklist
Product Support and Customer Service
For Further support visit our Contact Page Refer to UFS Drawing #997303 for valve ID # callouts.
! | ? | X | Description | Comments, Exceptions, & Notes |
Is the frame secured & level to the floor? | ||||
Are the ED paint manifolds level and true? | ||||
Do all match marks agree? | ||||
Does each valve the correct Valve ID Tag on it? | ||||
Do all valves work properly? | ||||
Has the unit passed the field leak check using water & the CIP? | ||||
Is each and every drain connected as required? | ||||
Has UF machine been cleaned and rinsed per Paint Vendor recommendations? | ||||
Is Paint Supply & Return pipes supported every 5’? | ||||
Are gauges properly facing Butterfly valves? | ||||
Does each UF Module have its correct Product & Spare Parts label? | ||||
Does each Bag Filter vessel have ‘only use glazed’ bag filters label? | ||||
Elements. Record pump serial number. | ||||
Make sure the paint is circulated for 24 -48 hours before the UF Elements are installed. Especially so, if held paint had been in a storage tank while the new UF machine was being installed. | ||||
System is now (only after Step 14 is completed) ready to install the UF Elements and begin machine start-up | ||||
Is laminated Valve ID & flow schematic on UF machine? |
Legend Description:
! - Needs Immediate attention ? - Some irregularity, probably ok X - Checked out fine
Notes: If customer provided the pre-filter system then for Step 11, make sure the vessels & related piping systems are leaked checked with water and have the proper glazed bag label installed on each vessel?