Upgrade to Tectron Anode Cells

Contents[Show]

Product Support and Customer Service

For Further support visit our Contact Page

General

If you are using box or crescent-shaped anode cells, you may consider upgrading your equipment when heavy maintenance of old cells is required. This document will assist you with some important considerations and ensure your conversion project goes smoothly. Developing the budget for your project will focus on three line items: Membrane Electrode Cells & Installation Accessories; Items Supplied by Others; and Installation Labor. The Membrane Electrode System (or anolyte system if cathodic paint is used) consists of: Holding Tank & Drain Piping Circulating Pump & Associated Gauges, etc. Conductivity Sensor & Controller Local Piping from the Holding Tank/Pump to the Manifolds Membrane Electrode Cells (including Cell support, fluid & electrical connections) Electrical Bus As a starting point, this document assumes the painted throughput will not change. If you are contemplating increasing the painted throughput, please request Bulletin #991108 Membrane Electrode System Design Book and ask your Sales & Service Engineer for a print-out of the Electrode Area Design & Engineering Summary for your ED System.

MEMBRANE ELECTRODE SYSTEM

Holding Tank

Generally, the volume of the existing tank is adequate and does not need to be changed. As a double check, the design sheet you will receive from your Sales & Service Engineer will have an estimate for the volume. NOTE: If your tank is at least 80% or more of the recommended volume, no change is required.

Circulating Pump, etc.

If your system is more than 8 years old, the pump may have to be replaced as circulation rates have increased since then. Your sheet will have a recommended flow rate.

Conductivity Sensor & Controller

The Sensor & Controller probably will need to be changed as conductivity levels have increased. As a standard, UFS Corporation only stocks 0-10,000 microSiemens/cm controllers. Another design change is to install the sensor in the pump discharge line to keep it cleaner.

Local Piping

If your pump will be upgraded, you will also need to increase the size of your discharge piping. At a minimum, the discharge piping needs to be 50 mm (2”). Large ED systems can use 75 mm (3”) pipe. The maximum flow velocity should not exceed 2.15 m/sec (7 ft/sec).

Membrane Electrode Cells

Typically, it may take up to five or six TECTRON Cells to replace a box cell or 2 to 3 TECTRON Cells for each crescent-shaped cell. For a complete technical discussion of the TECTRON Cell and its typical installation, request Bulletin #991001 TECTRON Anode Cell.

Electrical Bus

A DC rectifier is an important part of the ED system. The output of the rectifier is fed to the ED tank via a copper bus bar or individual leads. New cells are easily connected to a copper bus bar. On the other hand, if there is a cable for each old box/crescent cell, make sure to attach a copper set screw lug and use a star distribution pattern to the group of TECTRON Cells replacing it.

ITEMS SUPPLIED BY OTHERS

Generally, there is at least $1,000 to $2,000 in replacement parts and materials required. Your Sales & Service Engineer can prepare a pro forma estimate of these materials once your project is defined. Examples of the typical type of materials include : PVC pipe and PVC fittings; 41 mm (1-5/8”) square strut channel; angle iron; etc.

INSTALLATION LABOR

Generally, most end-users use their own maintenance staff to install all the equipment. In some cases, due to time and project constraints, they use a local contractor. UFSc can recommend third party vendors that are experienced with ED paint finishing systems retro-fits. UFSc can estimate labor for the project so you can develop a labor budget. Hours are estimated by trade: millwright, pipe fitter, electrician, etc.

DRAWINGS/DOCUMENTATION

UFSc supplies each retrofit customer with a Cell layout drawing. In addition, UFSc supplies typical General Arrangement drawings for mechanical, electrical, and piping. Your Sales & Service Engineer can assist you with choices and work with you to finalize a design. All the drawings and assistance are at no extra cost.

ON-SITE INSTALLATION

Generally, your Sales Engineer will be present at some point during the installation. The purpose of this visit is to answer questions and ensure the project is moving in the right direction. This on-site service is generally free, but in some cases, it will be quoted at $500 per day plus customary travel, lodging, and meal expenses. Each Sales Engineer carries a pager and can be paged 24 hours a day, 7 days a week.

BULLETIN 991107

 

 

 

 